October 29, 2026
The big one-story building at 805 Pine Grove Drive has looked like an empty grocery store ever since Lowe's Foods closed it in 2024. If you live in East & Mason, you pass it any time you take Pine Grove north from where it becomes Masonboro Loop Road. It sits on nearly five acres at the corner of Pine Grove Drive and Greenville Loop Road. Two busy roads meet there, along with a planned roundabout and a trail link where construction hasn't begun.
The building has a December 2026 opening target. The road and trail work planned around it doesn't have a construction contract yet. For at least a while, a new destination will open at an intersection that hasn't changed.
WilmingtonBiz reported on August 4 that Wave Wellness Real Estate LLC bought the 46,000-square-foot building for $7.5 million, with the deed recorded July 24, 2026. That price was $2.5 million more than the previous owner, Golden Ventures III LLC, paid for the site in November 2025. Back in February, the property was being marketed for lease with no final plan. The new owners told the Business Journal they expect to put $8.5 million into the building, and Monteith Construction is handling the upfit. The StarNews ran photos and renderings of the project on August 13.
Wave Aesthetics, an existing Wilmington medical aesthetics practice, is part of the ownership group. This building is meant to be the Wave Wellness flagship. According to WilmingtonBiz, the plans include:
The Wave Wellness FAQ says the current target opening is December 2026. No specific opening day has been announced. As of this Thursday, that target is about five weeks out.
The café and the coworking space may get a lot of local attention, but this isn't a store you can just walk into. The Wave Wellness homepage calls it "a capped club with a fixed number of memberships." The company says the founding memberships sold out in a few weeks. It's now offering 250 charter spots at $199 a month, locked for the first year, which it says is $1,200 less than a general membership. Once the cap is reached, new members go on a waitlist that the company expects could last two to three years.
The site was laid out for a grocery store. BlueCoast Commercial's offering memorandum, as WilmingtonBiz reported in February, lists 212 parking spaces with two entrances. It also gives daily traffic counts of 21,000 vehicles on Pine Grove Drive and 13,500 on Greenville Loop Road. Those counts were measured with the building empty. Once the parking lot is in use again, the traffic will still be going through the same intersection drivers use today.
The city has planned a dual-lane roundabout at Pine Grove Drive and Greenville Loop Road for years. It's part of the voter-approved transportation bond package the city calls Pine Grove South. The City of Wilmington project page describes the work:
The page lists the project value as "Contract not yet awarded." It says construction will begin in winter 2026 and take about 18 months. The same page lists right-of-way acquisition and final construction documents as summer 2025 milestones.
The newest public details come from a City Council work session on May 15, 2026. According to the meeting minutes, Mike Kozlosky, executive director of the Wilmington Urban Area Metropolitan Planning Organization, said design and permitting were complete and "the bid package is just about ready to go." He said Duke Energy had agreed to start clearing vegetation and moving poles after school let out. He estimated about three months for the construction itself. He also put the cost at about $4 million for the two intersections, not counting the Greenville Loop Trail.
Here's how the building and the road compare right now:
| Wave Wellness at 805 Pine Grove | Pine Grove South roundabout | |
|---|---|---|
| Status | Under construction by Monteith Construction | Designed and permitted; city page says contract not yet awarded |
| Stated timing | Target opening December 2026 | Construction to begin "winter 2026" |
| Duration | Upfit expected done by December | About 18 months on the city page; about three months in the May 15 minutes |
| Price tag | $7.5 million purchase, $8.5 million planned upfit | About $4 million for the two intersections, trail not included |
The city page and the May minutes don't agree on how long construction will take, and neither one explains the difference. Until the city announces a contract, what's known is the sequence. The building has a target month. The road work has a season on a city page, but no contract and no exact start date.
The roundabout contract affects more than traffic. It also holds up the last missing piece of the walking and biking network that meets at this corner.
The Greenville Loop Trail is a multi-use path of nearly four and a half miles that the city is building in phases. WECT laid out the phases on August 20:
City communications manager Amy Passaretti Willis told WilmingtonBiz in May that phase four "will be completed as part of the upcoming roundabout construction." That means the path segment running past the old grocery store, which would connect the Holly Tree trail to the rest of Greenville Loop, won't be built until the roundabout is.
The Masonboro Loop Trail, closer to East & Mason, is further along. The city describes it as a multi-use path running along Masonboro Loop Road from Navaho Trail to Pine Grove, with access to commercial areas such as Masonboro Station. In the same May interview, Willis said it would be finished over the summer and that "much of it is already open and walkable." She also said it would get a HAWK pedestrian crossing near the fire station and the shopping area. East & Mason's entrance is on Masonboro Loop just past that fire station, so that crossing would be right at the neighborhood.
From the neighborhood, then, the trail mostly works heading south. Heading north, it ends at Pine Grove Drive, before reaching the corner where the new club is opening.
Here is the order of events based on what has been announced so far. Wave Wellness is aiming for December, with no opening day set. The city's roundabout page still says the contract hasn't been awarded. The Pine Grove segment of the Greenville Loop Trail will be built along with the roundabout. If the city sticks to its 18-month estimate, a project starting this winter would wrap up sometime in 2028. If Kozlosky's three-month estimate holds, it could be done much sooner. A construction contract would be the first clear sign of which timeline applies.
There's one more project on Greenville Loop Road. The city is planning a public park on 25 acres at 6325 Greenville Loop Road. The project page says the amenities will be decided through public engagement and that development could be phased based on funding. Justin Carter, the city's director of design and construction, told WECT that the Greenville Loop Trail will help pedestrians get to that park.
For now, the corner of Pine Grove Drive and Greenville Loop Road has a building expected to open in December and an intersection that, as of the city's own page, has no construction contract or exact start date.
Changes like a reopened corner, a future roundabout and a nearly finished trail can affect how buyers see the homes along Masonboro Loop. If you'd like to know where your East & Mason home stands as these projects move ahead, The Warwick Team can walk you through it. Get a Free Home Valuation & Local Market Consultation.
Stay up to date on the latest real estate trends.
Providing our clients with a stress-free home buying or selling experience is our number one priority. With personalized service, our team will guide you through every step of the process. Our approach to helping clients buy or sell a home in the Wilmington area is simple—it starts with exceptional customer service. We take the time to listen, follow up, and answer questions directly, ensuring your experience is seamless and rewarding.